Review Type | Outcome | Est. Review Start Date | Completed |
---|---|---|---|
External Agencies Review | Approved | 09/16/2022 | 09/15/2022 |
Janelle Swanson
Send Email
|
|||
Miscellaneous
Outstanding
09/08/2022
1) Paperwork missing:
a. Combustion air worksheet (attached)
b. Makeup air worksheet (attached)
2) Hvac load calcs revisions needed:
a. The hvac load calcs should be combined as it is only one heating and cooling system not separate systems for the house and “apartment” above the garage.
b. Summer indoor temp must be a minimum of 75 degrees. Calcs currently at 69 degrees.
c. Winter outdoor temp must be set at -15 degrees. Calcs currently set at -4 degrees.
3) Energy certificate info needed:
a. Heating system is oversized more than 40%. Once hvac load calcs are recalculated, energy certificate must be updated with the appropriately sized unit.
b. Cooling system is undersized. Once hvac load calcs are recalculated, energy certificate must be updated with the appropriately sized unit.
c. Missing heat loss, heat gain, and cooling load.
d. Missing seer/eer value of cooling system.
e. Mechanical ventilation system for a house of 5,933 sq ft and 5 bedrooms requires a total cfm of 210 and continuous cfm of 105.
4) Plans missing/need:
a. Engineering required for steel beam over 16’ patio door to screen porch.
b. Specs required for 8x8 cedar beam supporting front porch ridge beam.
c. Engineering required for the back basement foundation wall. This foundation wall is not laterally supported at the top as the trusses bear on an interior wall in front of the foundation wall as shown in cross sections
1/7, 1/8, and 1/9 on pages 7, 8, and 9. There is no bearing on top of the foundation wall nor connected per code or the engineered foundation guide therefore, this wall requires an engineered design.
d. 8’ patio door to rear porch requires a 3”x11.25” minimum header to comply with the engineered wall bracing plan
e. Both cased openings on right side kitchen wall require a (2)2x12 minimum header to comply with the engineered wall bracing plan
f. Cross section 1/9 shows a 14’ tall wall at the front of the kitchen area. The engineered wall bracing is based on the 2020 MSBC per the described scope and there is no specific consideration spelled out by the
engineer for the braced wall panel located on this tall wall. The building code does not allow wall bracing on walls greater than 12’ in height so this must be addressed by the engineer and added to the engineered
wall bracing plan.
Regards,
Nicolas Qualle
Code Official
MN CBO#: BO002752
MNSPECT, LLC., A SAFEbuilt Company
Helping You Comply With The Code
235 First St. W.
Waconia, MN 55367
Office: 952-442-7520
www.mnspect.com
|
|||
Planning Department Review | Approved | 09/14/2022 | 09/13/2022 |
Nathan Hall
Send Email
|
|||
Miscellaneous
Outstanding
09/08/2022
Please apply for the attached Accessory Dwelling Unit with the Zoning Department.
|
|||
Building Review | Not Required | 09/14/2022 | 09/08/2022 |
Janelle Swanson
Send Email
|
|||
Miscellaneous
Outstanding
09/08/2022
See External Review for corrections
|
|||
Environmental Health Review | Approved | 08/16/2022 | 08/19/2022 |
Jesse Krzenski
Send Email
|
|||
Fencing/Staking
Resolved
08/19/2022
Both the primary and alternate soil dispersal areas shall be fenced prior to applying for a permit to construct an SSTS. The fence shall consist of four-foot high orange construction fence, wooden snow fence, or two strands of weatherproof high-visibility roping attached to posts placed no more than 20 feet apart with either high visibility ribbon at least one-half inch wide tied to the rope no more than 6 feet apart or signs no smaller than 16 inches by 20 inches no more than 20 feet apart, that clearly identify the soil dispersal area and prohibit trespass. The fencing or roping and signs shall be clearly visible at least two feet above surrounding vegetation or snow. The choice between fencing and roping with signs shall be at the discretion of the designer and property owner and should take into consideration any risk such barrier may present. The stakes shall be clearly visible at least two feet above surrounding vegetation or snow and the stake labeling shall be legible.
|
|||
Building Review | Failed | 08/16/2022 | 08/19/2022 |
Jeremy Schussler
Send Email
|
|||
Miscellaneous
Carry Forward
09/08/2022
See External Review for corrections
|
|||
External Agencies Review | Failed | 08/18/2022 | 08/19/2022 |
Jeremy Schussler
Send Email
|
|||
Miscellaneous
Carry Forward
09/08/2022
1) Paperwork missing:
a. Combustion air worksheet (attached)
b. Makeup air worksheet (attached)
2) Hvac load calcs revisions needed:
a. The hvac load calcs should be combined as it is only one heating and cooling system not separate systems for the house and “apartment” above the garage.
b. Summer indoor temp must be a minimum of 75 degrees. Calcs currently at 69 degrees.
c. Winter outdoor temp must be set at -15 degrees. Calcs currently set at -4 degrees.
3) Energy certificate info needed:
a. Heating system is oversized more than 40%. Once hvac load calcs are recalculated, energy certificate must be updated with the appropriately sized unit.
b. Cooling system is undersized. Once hvac load calcs are recalculated, energy certificate must be updated with the appropriately sized unit.
c. Missing heat loss, heat gain, and cooling load.
d. Missing seer/eer value of cooling system.
e. Mechanical ventilation system for a house of 5,933 sq ft and 5 bedrooms requires a total cfm of 210 and continuous cfm of 105.
4) Plans missing/need:
a. Engineering required for steel beam over 16’ patio door to screen porch.
b. Specs required for 8x8 cedar beam supporting front porch ridge beam.
c. Engineering required for the back basement foundation wall. This foundation wall is not laterally supported at the top as the trusses bear on an interior wall in front of the foundation wall as shown in cross sections
1/7, 1/8, and 1/9 on pages 7, 8, and 9. There is no bearing on top of the foundation wall nor connected per code or the engineered foundation guide therefore, this wall requires an engineered design.
d. 8’ patio door to rear porch requires a 3”x11.25” minimum header to comply with the engineered wall bracing plan
e. Both cased openings on right side kitchen wall require a (2)2x12 minimum header to comply with the engineered wall bracing plan
f. Cross section 1/9 shows a 14’ tall wall at the front of the kitchen area. The engineered wall bracing is based on the 2020 MSBC per the described scope and there is no specific consideration spelled out by the
engineer for the braced wall panel located on this tall wall. The building code does not allow wall bracing on walls greater than 12’ in height so this must be addressed by the engineer and added to the engineered
wall bracing plan.
Regards,
Nicolas Qualle
Code Official
MN CBO#: BO002752
MNSPECT, LLC., A SAFEbuilt Company
Helping You Comply With The Code
235 First St. W.
Waconia, MN 55367
Office: 952-442-7520
www.mnspect.com
|
|||
Planning Department Review | Failed | 08/16/2022 | 08/18/2022 |
Nathan Hall
Send Email
|
|||
Miscellaneous
Carry Forward
09/08/2022
Please apply for the attached Accessory Dwelling Unit with the Zoning Department.
|
|||
Erosion Control Plan Review | Approved | 08/16/2022 | 08/11/2022 |
Collin Schoenecker
Send Email
|
|||
Erosion Control Field Review | Not Required | 08/16/2022 | 08/11/2022 |
Collin Schoenecker
Send Email
|
Paid Fees | Amount | Paid | Owing | Date Paid |
---|---|---|---|---|
Building Permit Fee (NEW HOME) | $8,031.65 | $8,031.65 | Paid | 09/15/2022 |
Building Permit State Surcharge | $624.00 | $624.00 | Paid | 09/15/2022 |
Plan Check Fee (Building) | $5,220.57 | $5,220.57 | Paid | 09/15/2022 |
Mechanical Permit Fee - Fireplace or Wood Stove | $76.00 | $76.00 | Paid | 09/15/2022 |
Mechanical Permit Fee/New System | $171.00 | $171.00 | Paid | 09/15/2022 |
Plumbing Permit Fee/New System | $171.00 | $171.00 | Paid | 09/15/2022 |
Septic New for SSTS | $775.00 | $775.00 | Paid | 09/15/2022 |
ESC Review Fee for Accessory Structures | $130.00 | $130.00 | Paid | 09/15/2022 |
ESC Escrow | $1,000.00 | $1,000.00 | Paid | 09/15/2022 |
911 Address Marker Fees/New Home | $110.00 | $110.00 | Paid | 09/15/2022 |
Septic Inspection/Reinspection | $110.00 | $110.00 | Paid | 09/15/2022 |
Outstanding Fees | Amount | Paid | Owing | Date Paid |
No outstanding fees. | ||||
Totals: | $16,419.22 | $16,419.22 | $0.00 |
$0.00
Inspection | Outcome | Requested | Scheduled | Date Inspected |
---|---|---|---|---|
Septic Drainfield Installation | Passed | 09/27/2022 | ||
Septic Tank Installation | Passed | 09/28/2022 | ||
Septic Final Cover | Passed | 09/28/2022 | ||
Footing | Passed | 10/6/2022 (10:30 to 11:00) | 10/6/2022 (AM) | 10/06/2022 |
Poured Wall Forms | Passed | 10/19/2022 (8:30 to 9:00) | 10/19/2022 (AM) | 10/19/2022 |
Foundation | Passed | 10/25/2022 (3:00 to 3:30) | 10/25/2022 (PM) | 10/25/2022 |
Plumbing Rough-in | Partial Pass | 12/20/2022 (8:30 to 9:00) | 12/20/2022 (AM) | 12/20/2022 |
Miscellaneous
Carry Forward
12/20/2022
Below grade DWV appears ok. Air test passed.
|
||||
Miscellaneous
Carry Forward
12/20/2022
Above grade RI not ready for inspection.
|
||||
Radon Above Grade Rough In | Failed | 12/20/2022 (8:30 to 9:00) | 12/20/2022 (AM) | 12/20/2022 |
Miscellaneous
Carry Forward
12/20/2022
Not ready for inspection yet.
|
||||
Radon/Vapor Barrier Under Slab | Passed | 12/21/2022 (3:00 to 3:30) | 12/21/2022 (PM) | 12/21/2022 |
Plumbing Rough-in | Partial Pass | 1/9/2023 (1:30 to 2:00) | 1/9/2023 (PM) | 01/09/2023 |
Miscellaneous
Carry Forward
01/09/2023
Below grade DWV appears ok. Air test passed.
|
||||
Miscellaneous
Carry Forward
01/09/2023
Above grade RI not ready for inspection.
|
||||
Radon Above Grade Rough In | Failed | 1/10/2023 (10:00 to 10:30) | 1/10/2023 (AM) | 01/10/2023 |
Miscellaneous
Carry Forward
01/10/2023
Not ready for inspection yet.
|
||||
Radon/Vapor Barrier Under Slab | Passed | 1/10/2023 (10:00 to 10:30) | 1/10/2023 (AM) | 01/10/2023 |
Framing/Weather Barrier/Roof | Partial Pass | 2/8/2023 (1:00 to 1:30) | 2/8/2023 (PM) | 02/08/2023 |
Miscellaneous
Carry Forward
02/08/2023
House wrap and shingles ok - Metal roofs not installed yet. Framing not inspected. Partial pass
|
||||
Miscellaneous
Carry Forward
02/08/2023
Mechanical exhaust caps not installed on roof yet.
|
||||
Mechanical Rough-in | Passed | 2/8/2023 (1:00 to 1:30) | 2/8/2023 (PM) | 02/08/2023 |
Radon Above Grade Rough In | Passed | 2/17/2023 (9:30 to 10:00) | 2/17/2023 (AM) | 02/17/2023 |
Miscellaneous
Outstanding
01/10/2023
Not ready for inspection yet.
|
||||
Plumbing Rough-in | Partial Pass | 2/17/2023 (9:30 to 10:00) | 2/17/2023 (AM) | 02/17/2023 |
Miscellaneous
Resolved
02/17/2023
Below grade DWV appears ok. Air test passed.
|
||||
Miscellaneous
Resolved
02/17/2023
Above grade RI not ready for inspection.
|
||||
Miscellaneous
Carry Forward
02/17/2023
Air test needed for supply.
|
||||
Miscellaneous
Carry Forward
02/17/2023
Above ground DWV is good.
|
||||
Framing/Weather Barrier/Roof | Partial Pass | 2/21/2023 (9:00 to 9:30) | 2/21/2023 (AM) | 02/21/2023 |
Miscellaneous
Resolved
02/21/2023
House wrap and shingles ok - Metal roofs not installed yet. Framing not inspected. Partial pass
|
||||
Miscellaneous
Resolved
02/21/2023
Mechanical exhaust caps not installed on roof yet.
|
||||
Miscellaneous
Carry Forward
02/21/2023
Metal roofs not installed yet.
|
||||
Miscellaneous
Inspector Comment
02/21/2023
Okay to insulate.
|
||||
Insulation | Partial Pass | 3/3/2023 (8:30 to 9:00) | 3/3/2023 (AM) | 03/03/2023 |
Miscellaneous
Carry Forward
03/03/2023
Open voids in the draft stopping.
|
||||
Miscellaneous
Carry Forward
03/03/2023
Garage not insulated yet.
|
||||
Miscellaneous
Carry Forward
03/03/2023
Main floor and loft living space insulation/vapor is good. Partial Pass
|
||||
Fireplace Rough-In | Partial Pass | 3/3/2023 (8:00 to 8:30) | 3/3/2023 (AM) | 03/03/2023 |
Miscellaneous
Resolved
04/27/2023
Main floor gas FP's are good. The FP in the porch is not installed yet.
|
||||
Miscellaneous
Resolved
04/27/2023
Lower level wood FP on separate permit.
|
||||
Gasline | Failed | 3/3/2023 (8:00 to 8:30) | 3/3/2023 (AM) | 03/03/2023 |
Miscellaneous
Carry Forward
03/03/2023
Pressure gauges were at zero at the time of the inspection.
|
||||
Insulation | Partial Pass | 3/6/2023 (1:00 to 1:30) | 3/6/2023 (PM) | 03/06/2023 |
Miscellaneous
Carry Forward
03/06/2023
Open void in the draft stopping above plenum.
|
||||
Miscellaneous
Resolved
03/06/2023
Garage not insulated yet.
|
||||
Miscellaneous
Resolved
03/06/2023
Main floor and loft living space insulation/vapor is good. Partial Pass
|
||||
Gasline | Failed | 03/06/2023 | ||
Miscellaneous
Carry Forward
03/06/2023
Pressure gauges were at zero at the time of the inspection.
|
||||
Gasline | Passed | 3/8/2023 (2:00 to 2:30) | 3/8/2023 (PM) | 03/09/2023 |
Miscellaneous
Outstanding
03/06/2023
Pressure gauges were at zero at the time of the inspection.
|
||||
Insulation | Passed | 03/14/2023 | ||
Miscellaneous
Resolved
03/14/2023
Open void in the draft stopping above plenum.
|
||||
Plumbing Rough-in | Passed | 03/14/2023 | ||
Miscellaneous
Resolved
03/14/2023
Air test needed for supply.
|
||||
Miscellaneous
Resolved
03/14/2023
Above ground DWV is good.
|
||||
Interior Wall Bracing Panels | Passed | 3/14/2023 (1:00 to 1:30) | 3/14/2023 (PM) | 03/14/2023 |
Fireplace Rough-In | Passed | 4/27/2023 (3:00 to 3:30) | 4/27/2023 (PM) | 04/27/2023 |
Miscellaneous
Resolved
04/27/2023
Main floor gas FP's are good. The FP in the porch is not installed yet.
|
||||
Miscellaneous
Resolved
04/27/2023
Lower level wood FP on separate permit.
|
||||
Lath | Not Required | 7/19/2023 (1:30 to 2:00) | 7/19/2023 (PM) | 07/20/2023 |
Plumbing Final | Passed | 7/19/2023 (2:00 to 2:30) | 7/19/2023 (PM) | 07/20/2023 |
Mechanical Final | Passed | 7/19/2023 (1:30 to 2:00) | 7/19/2023 (PM) | 07/20/2023 |
Radon Final | Passed | 7/19/2023 (2:30 to 3:00) | 7/19/2023 (PM) | 07/20/2023 |
Framing/Weather Barrier/Roof | Passed | 7/19/2023 (2:00 to 2:30) | 7/19/2023 (PM) | 07/20/2023 |
Miscellaneous
Resolved
07/20/2023
Metal roofs not installed yet.
|
||||
Final | Failed | 7/24/2023 (3:00 to 3:30) | 7/24/2023 (PM) | 07/24/2023 |
Miscellaneous
Carry Forward
07/24/2023
Siding not completed on rear of home adjacent to pool
|
||||
Electrical Final inspection
Carry Forward
07/24/2023
Electrical Final Inspection required
|
||||
Miscellaneous
Carry Forward
07/24/2023
Fire blocking required on basement mechanical room a interior wall where it meets the floor joists
|
||||
Miscellaneous
Carry Forward
07/24/2023
Foundation insulation is exposed by pool
|
||||
Insulation card
Carry Forward
07/24/2023
Insulation certificate MEC 1322.0103
|
||||
Miscellaneous
Carry Forward
07/24/2023
Submit blower door test, ok to email to thussong@co.Scott.mn.us
|
||||
Final | Partial Pass | 07/27/2023 | ||
Miscellaneous
Carry Forward
07/27/2023
Siding not completed on rear of home adjacent to pool
|
||||
Electrical Final inspection
Carry Forward
07/27/2023
Electrical Final Inspection required
|
||||
Miscellaneous
Resolved
07/27/2023
Fire blocking required on basement mechanical room a interior wall where it meets the floor joists
|
||||
Miscellaneous
Carry Forward
07/27/2023
Foundation insulation is exposed by pool
|
||||
Insulation card
Resolved
07/27/2023
Insulation certificate MEC 1322.0103
|
||||
Miscellaneous
Resolved
07/27/2023
Submit blower door test, ok to email to thussong@co.Scott.mn.us
|
||||
Final | Partial Pass | 07/27/2023 | ||
Miscellaneous
Carry Forward
07/27/2023
Siding not completed on rear of home adjacent to pool
|
||||
Electrical Final inspection
Resolved
07/27/2023
Electrical Final Inspection required
|
||||
Miscellaneous
Carry Forward
07/27/2023
Foundation insulation is exposed by pool
|
||||
Final | Passed | 9/1/2023 (3:00 to 3:30) | 9/1/2023 (PM) | 09/01/2023 |
Miscellaneous
Resolved
09/01/2023
Siding not completed on rear of home adjacent to pool
|
||||
Miscellaneous
Resolved
09/01/2023
Foundation insulation is exposed by pool
|
||||
Erosion Control Final | Passed | 09/28/2023 |